Factory acceptance testing, commonly called FAT, is the structured opportunity to verify machinery before it leaves the supplier's facility. For a concrete block press or integrated line, a convincing FAT does more than show that the equipment can cycle under power. It establishes which functions were tested, the conditions used, the results observed and the issues still open before shipment. A buyer who defines acceptance evidence early can avoid discovering a major scope disagreement only after foundations and utilities are complete.
Agree the acceptance scope before manufacture is finished
The purchase contract and technical specification should identify equipment within the FAT boundary. A test for the forming press may not include the production mixer, automatic curing system, full pallet loop or factory-wide safety interfaces. Those exclusions are legitimate only when both parties understand them. Mark each function as witnessed, simulated, verified by documents or deferred until site acceptance testing.
Acceptance criteria should be measurable and feasible under the factory conditions available. “Machine works well” is not a useful criterion. Examples include successful operation through specified sequences, recorded sensor responses, documented interlock behaviour and repeatability of key movements. A realistic plan also explains what cannot be established until the equipment is assembled at the final site.
Build a traceability matrix from specification to evidence
List each contractual requirement, the planned test, the expected outcome and the responsible witness. A matrix prevents attractive demonstration runs from replacing verification of less visible functions such as access protection, automatic recovery and documentation completeness. Record the machine identification number and software version against each relevant result. This creates a durable connection between the purchased configuration and the evidence received.
Documentation can be reviewed before any machine movement begins. Check general arrangement drawings, electrical diagrams, hydraulic schematics, parts lists, manuals, installation conditions and utility schedules. Confirm that as-built revisions are included, not only preliminary designs. An incomplete document package should be identified as an open item with an owner and completion date.
Test the operating sequence with realistic products
Whenever practical, use moulds and product geometry representative of the buyer's intended production. A press can cycle smoothly with an uncomplicated mould while struggling with an unusual kerbstone profile or thin-walled block. Record the material type, moisture condition, mould identification and production pallet configuration so that the demonstration can be interpreted correctly. If representative materials are not available, state that limitation rather than treating the run as proof of finished-product capability.
Observe filling, compaction, demoulding, pallet discharge and recovery from normal pauses. Mark product samples and retain photographs of defects and settings. A short peak-speed run should not be presented as a sustained shift-capacity result. Extended performance tests need agreed duration, product acceptance criteria and rules for counting stops and rejects.
Witness faults and protective functions safely
A FAT plan should include agreed tests of alarms, emergency stops, guard status, permitted modes and expected safe responses. Hazardous fault simulation belongs under an approved test procedure managed by qualified personnel. The purpose is to confirm that a protective arrangement behaves as designed, not to bypass it for the sake of demonstration. A machine that runs well in automatic mode is not necessarily safe to clean, adjust or recover after a blockage.
Test sensible failure cases such as loss of a non-safety sensor, missing pallet confirmation or a simulated unavailable downstream station. Check whether the fault message points to the actual problem and whether restart requires the intended operator acknowledgement. Keep a separate record of any deferred safety validations that must be completed after installation.
Record defects and control shipment decisions
Create an open-issues register with a unique number, description, severity, corrective action, owner and target date. Distinguish cosmetic defects, documentation gaps, performance deviations and issues that must block shipment. A conditional acceptance should explicitly say what remains incomplete and how re-verification will occur. Silence in a meeting should never be interpreted as approval of unresolved deviations.
Photographs, video clips, instrument readings and signed test sheets should be organised by requirement. Record any substituted component or changed software version. If the supplier corrects a defect after witnessing, specify whether the affected test must be repeated. This discipline reduces disputes and creates an effective starting point for commissioning.
Understand the difference between FAT and site acceptance
Site acceptance testing, or SAT, verifies installed behaviour under actual plant utilities, foundations, material flow and operating conditions. Some interfaces can be checked only after connection to the upstream batching system and downstream curing equipment. The two tests therefore complement one another; a successful FAT does not replace SAT. The contract should define responsibilities for unloading, erection, electrical connection, software integration and final acceptance.
Before leaving the factory, confirm shipping preparation, transport restraints, spare-part packaging and preservation instructions. Verify that any reference settings or recipes are backed up and delivered with the machine. Small omissions can cause avoidable delays when the installation team is ready to start.
Turn the FAT report into a commissioning tool
The final FAT dossier should include the agreed test plan, results, open items, software and drawing revisions, and retained sample or measurement records. Use the dossier to prepare utilities, training and SAT activities. It should remain accessible to maintenance and quality personnel rather than disappear into procurement archives. Good acceptance documentation makes the first production weeks easier to manage and future troubleshooting faster.